CORENET X vs CORENET 2.0: Key Differences and the 2026 Timeline

CORENET X vs CORENET 2.0: Key Differences and the 2026 Timeline

11 min read

CORENET 2.0 is Singapore’s existing e-submission system for building-related applications, where Qualified Persons (QPs) prepare and send plans to each regulatory agency; CORENET X is its multi-agency replacement, built around coordinated BIM models in IFC+SG format and a small number of submission gateways. From 1 October 2026, CORENET X is mandatory for new projects of 5,000 sqm GFA and above, while smaller projects can continue in CORENET 2.0. This guide compares the two systems and explains what the change means for your BIM submission workflow.

On this page
  1. What Is CORENET 2.0?
  2. What Is CORENET X?
  3. CORENET 2.0 vs CORENET X: Comparison Table
  4. CORENET 2.0 and CORENET X: Key Differences Explained
  5. When Is CORENET X Mandatory?
  6. Official CORENET Portals and Helpdesks
  7. What This Means for Your BIM Submission Workflow
  8. Frequently Asked Questions
  9. References

For the data format behind CORENET X submissions, see What is IFC-SG.

What Is CORENET 2.0?

The official CORENET 2.0 e-Submission System describes itself as “a 24×7 e-service that facilitate[s] the electronic submission and processing of building related applications and documents anytime, anywhere in a secured environment using internet as the delivery medium.” Its help centre explains that CORENET 2.0 is “a major technology refresh” of the original CORENET e-Submission System, intended to improve the user experience and “serve the industry prior to the implementation of CORENET X” (Building and Construction Authority).

Under CORENET 2.0, QPs submit drawings and documents to each regulatory agency – BCA, URA, SCDF, PUB, NEA and others. Each agency reviews its own submission on its own track and issues its own approval. The CORENET X website notes that under this process projects often face “more than 20 approval touchpoints”, with responses from each agency received separately. It works, but the burden of coordinating those parallel approvals sits with the project team, and inconsistencies between drawing sets are often discovered late.

Some practical features of CORENET 2.0, according to official sources:

  • Submission preparation uses ES Pro, a downloadable application (CORENET X key differences page).
  • Who submits: the system mainly serves QPs, who complete each agency’s application form. For URA planning applications, only QPs with a valid Practising Certificate can submit, and plans and forms are signed with a Netrust digital certificate (URA).
  • Fees are paid separately under each agency’s system.

Who still uses CORENET 2.0 after 1 October 2026?

According to the joint BCA and URA circular Updates to CORENET X Implementation Plan (APPBCA-2026-12 / URA/PB/2026/08-DCG, 23 July 2026), CORENET 2.0 remains in use for three groups of projects:

  • Projects below 5,000 sqm GFA. These are not required to onboard the CORENET X Gateway Processes and may continue in CORENET 2.0, where 2D or lightweight BIM is allowed. Using CORENET X is voluntary for them.
  • Projects of 5,000 sqm and above that commenced submissions in CORENET 2.0 by 30 September 2026. These may continue there for now.
  • Other ongoing projects. The circular says these may continue in CORENET 2.0 “until further details are announced”. Here, ongoing projects means those seeking Design Gateway-equivalent clearances (such as Provisional Permission) in CORENET 2.0.

The circular also says agencies are working to streamline the submission process for projects below 5,000 sqm, with details to follow. Check the latest circulars before you decide which system to use.

What Is CORENET X?

CORENET X is described by its official site as “a co-creation effort between the public agencies and industry to transform the regulatory landscape”, implemented progressively in phases. It names four key changes to the submission process: a new submission process, BIM submission in IFC+SG format, the CORENET X Submission Portal and the CORENET X Code of Practice. Seven agencies review submissions: BCA, LTA, NEA, NParks, PUB, SCDF and URA.

Instead of separate drawing sets, the project team submits coordinated BIM models in IFC+SG format, an openBIM standard that carries Singapore-specific regulatory information inside the model. CORENET X also accepts non-BIM submissions alongside the models. The new Regulatory Approval for Building Works (RABW) process consolidates the many approval touchpoints into “3 key sequential submission gateways”. At each gateway, agencies review the coordinated submission from multiple disciplines together, so cross-agency conflicts can be resolved early.

The CORENET 2.0 help centre puts the difference simply: CORENET X aims to change the current practice of QPs dealing separately with multiple regulatory agencies and producing different versions of building plans. Instead, the project team can collaborate and review designs in the model together, detect possible major conflicts before construction, and produce a coordinated BIM model for submission and regulatory approval.

Building works follow Pre-Submission Consultation, then the Design Gateway, the Piling Gateway (where applicable), the Construction Gateway and the Completion Gateway. Independent Submissions and a Direct Submission Process also exist. Our guide to the CORENET X Code of Practice and its gateways explains what each stage needs.

CORENET 2.0 vs CORENET X: Comparison Table

AspectCORENET 2.0CORENET X
Who uses itProjects below 5,000 sqm GFA, and projects that commenced CORENET 2.0 submissions by 30 Sep 2026New projects of 5,000 sqm GFA and above from 1 Oct 2026 (30,000 sqm and above since 1 Oct 2025)
What you submitDrawings and documents; 2D or lightweight BIM allowed below 5,000 sqmCoordinated BIM models in IFC+SG format, plus non-BIM submissions
Review processSeparate submissions and responses per agency; often 20+ approval touchpointsMulti-agency review at sequential submission gateways
Submission preparationES Pro softwareFully web-based Submission Portal
UsersMainly QPs; only QPs add assistantsQPs plus other project members, who log in to accept appointments and make declarations
Appointing project membersOutside the system, often with wet-ink signaturesFully digital
FormsQPs complete each agency’s application formMembers enter their information; forms are auto-populated
FeesPaid separately under each agency’s systemPaid through the portal before submission to agencies
Official sitecorenet2-ess.gov.sginfo.corenet.gov.sg

Sources: CORENET X key differences page, the July 2026 BCA/URA circular and URA.

CORENET 2.0 and CORENET X: Key Differences Explained

  • What you submit: CORENET 2.0 accepts drawings and documents. CORENET X requires BIM models exported to IFC+SG for projects of 5,000 sqm and above.
  • How agencies review: CORENET 2.0 runs separate reviews per agency. CORENET X uses a multi-agency, gateway-based submission process in which agencies review coordinated submissions together.
  • Validation: CORENET X lets QPs run a Pre-Submission Check with the Model Checker, and CORENET X support encourages at least one round before submitting. It is a supplementary tool and, as CORENET X states, not a replacement for manual review.
  • Collaboration: in CORENET 2.0, QPs work in silos. In CORENET X, all project members can view the project’s submissions, and the initiating member acts as submission coordinator.
  • Workflow impact: CORENET 2.0 lets BIM remain optional behind the drawings. CORENET X makes the BIM model itself the regulatory deliverable.

When Is CORENET X Mandatory?

CORENET X submission became mandatory on 1 October 2025 for new projects of 30,000 sqm GFA and above. From 1 October 2026, the mandate extends to new projects with GFA of 5,000 sqm and above (BCA circular APPBCA-2026-12 / URA circular URA/PB/2026/08-DCG, 23 July 2026). “New projects” covers new buildings, additions or extensions, and major addition and alteration works at or above that GFA. IFC+SG is mandatory at 5,000 sqm and above. Projects below 5,000 sqm GFA are not required to onboard the Gateway Processes and may continue through CORENET 2.0 for now.

The transition point therefore depends on your project size and submission stage, and the threshold has already been revised once, from 30,000 sqm down to 5,000 sqm. See CORENET X from 1 October 2026 and the 5,000m² threshold for the detail.

Official CORENET Portals and Helpdesks

Use the official .gov.sg sites below. Logins and access steps are explained on each portal, so follow the instructions there.

What you needCORENET 2.0CORENET X
Main sitewww.corenet2-ess.gov.sg (includes the login page, announcements and software downloads)info.corenet.gov.sg
Submission portalVia the CORENET 2.0 siteportal.corenet.gov.sg
Help and FAQsCORENET 2.0 self-help troubleshooting guidessupport.corenet.gov.sg (guides, known issues and helpdesk)
EnquiriesCORENET 2.0 Contact Usgo.gov.sg/cxenquiry (per the July 2026 circular)
GuidanceAgency pages, such as URA’s CORENET 2 guideCORENET X Code of Practice, IFC+SG Knowledge Hub and Training Environment

As the CORENET 2.0 site reminds users, government officials will never ask you to transfer money or disclose bank login details over the phone, and official links end in .gov.sg.

What This Means for Your BIM Submission Workflow

The practical shift is simple to state and hard to do: your BIM model must now be good enough to be reviewed by regulators, not just good enough to print drawings from. That means disciplined coordination across architectural, structural and MEP models, clean IFC+SG export, and an information structure that survives validation. The approval process under CORENET X rewards teams that build submission readiness into the workflow early, and punishes teams that leave model quality to the end. Our guide to common IFC-SG validation errors covers what typically fails.

If your project is moving from CORENET 2.0 habits to CORENET X, three steps help:

  1. Confirm which system applies – check GFA, project type and whether submissions began in CORENET 2.0 by 30 September 2026.
  2. Set up IFC+SG early – configure your authoring tool (Revit, Archicad, Tekla or others) with the IFC+SG parameters and export settings, and check the current IFC+SG Excel Mapping File (the industry mapping of entities, property sets and values) before design development, not at submission.
  3. Coordinate before each gateway – federate and check discipline models, then run the Pre-Submission Check before submitting to agencies.

Beyond+ supports project teams through this transition with CORENET X BIM e-submission support: model readiness reviews, IFC+SG structuring, and coordination discipline ahead of each gateway.

Frequently Asked Questions

Can I still submit through CORENET 2.0?

Yes, in some cases. Projects with GFA below 5,000 sqm are not required to onboard the Gateway Processes and may continue through CORENET 2.0. Projects of 5,000 sqm and above that commenced submissions in CORENET 2.0 by 30 September 2026 may also continue there for now. New projects of 5,000 sqm and above starting from 1 October 2026 must use CORENET X.

Will CORENET 2.0 be replaced?

The CORENET 2.0 help centre states that CORENET 2.0 “will eventually be replaced by CORENET X”. For ongoing projects, the July 2026 circular says they may continue in CORENET 2.0 until further details are announced.

What is IFC-SG?

IFC-SG (IFC+SG) is Singapore’s localisation of the openBIM IFC standard, based on the IFC4 schema. It defines how regulatory information, including spaces, elements, property sets and values, must be structured in the model so agencies can validate and review it.

Who makes the submission?

As with CORENET 2.0, Qualified Persons (QPs) remain responsible. Under CORENET X, however, other project members also log in to accept appointments and make declarations, and the team submits coordinated models through one portal rather than separate drawing sets to each agency.

Does CORENET X change design work itself?

Indirectly, yes. Because the model is validated, modelling standards, naming and coordination quality now affect regulatory approval, not just construction. Our CORENET X submission checklist covers what to prepare before each gateway. For the complete picture, see our CORENET X requirements and timeline guide.

Not sure which system your project falls under? Tell us your project size, stage and gateway – talk to Beyond+ or explore our BIM services.

References

  1. CORENET 2.0 e-Submission System. Government of Singapore. https://www.corenet2-ess.gov.sg/
  2. 1.1 What is CORENET 2.0? Building and Construction Authority (CORENET 2.0 Help Centre). https://support.corenet2-ess.gov.sg/hc/en-us/articles/24009054255641-1-1-What-is-CORENET-2-0
  3. 1.2 What is the difference between CORENET 2.0 and CORENET X? Building and Construction Authority (CORENET 2.0 Help Centre). https://support.corenet2-ess.gov.sg/hc/en-us/articles/24009099937561-1-2-What-is-the-difference-between-CORENET-2-0-and-CORENET-X
  4. Updates to CORENET X Implementation Plan (APPBCA-2026-12 / URA/PB/2026/08-DCG). BCA and URA, 23 July 2026. https://www.ura.gov.sg/guidelines/circulars/dc26-08/
  5. CORENET X vs CORENET 2.0: Key Differences Between CORENET 2 System and CORENET X Submission Portal. CORENET X. https://info.corenet.gov.sg/submission-portal-resource/more/corenet-x-and-corenet-2.0–key-differences
  6. About the New Submission Process. CORENET X. https://info.corenet.gov.sg/regulatory-process/about-the-new-submission-process
  7. CORENET X home page. CORENET X. https://info.corenet.gov.sg/
  8. CORENET X Code of Practice (Fourth Edition, 2026-09). CORENET X. https://info.corenet.gov.sg/regulatory-process/corenet-x-code-of-practice
  9. Corenet 2 – Submitting development applications via CORENET 2. Urban Redevelopment Authority. https://www.ura.gov.sg/guidelines/development-control/planning-permission/dasub/cn2/
  10. Plan Lodgment Application. Urban Redevelopment Authority. https://www.ura.gov.sg/guidelines/development-control/planning-permission/plan-lodgment-application/
  11. Can QPs use the MC to check their BIM models before submitting via CORENET X? CORENET X Support. https://support.corenet.gov.sg/hc/en-us/articles/13750763534095-Can-QPs-use-the-MC-to-check-their-BIM-models-before-submitting-via-CORENET-X
  12. Is it necessary for QPs to review the design after the BIM models are checked by MC MVP? CORENET X Support. https://support.corenet.gov.sg/hc/en-us/articles/16336534594191-Is-it-necessary-for-QPs-to-review-the-design-after-the-BIM-models-are-checked-by-MC-MVP
  13. CORENET X Support Centre. CORENET X. https://support.corenet.gov.sg/
  14. Self-Help Troubleshooting Guides. CORENET 2.0 Help Centre. https://support.corenet2-ess.gov.sg/hc/en-us/articles/21700510832921-Self-Help-Troubleshooting-Guides