14 min read
Shop drawings show how a contractor or fabricator will make and install part of the works before it is built; as-built drawings (or an as-built model) record what was actually built once the work is complete. One looks forward and gets a design accepted for fabrication. The other looks back and becomes the record for the owner, the facility manager and, in Singapore, the agencies at the CORENET X Completion Gateway. On a BIM project, both can come from the same coordinated model, provided it is kept up to date.
This guide compares design drawings, shop drawings, combined services drawings (CSD) and as-built drawings. It covers who prepares and reviews each on a Singapore project, what a good shop drawing contains, and how BIM coordination produces both sets of drawings.
“Construction drawings” is often used for every sheet on site, but the drawings come from different parties, at different stages, for different reasons. BCA’s Singapore BIM Guide Version 2 lists shopdrawings, construction and fabrication models and the as-built model as separate BIM deliverables. It also treats design drawings, tender drawings, working drawings and as-built drawings as distinct sets.
During the design phase, design drawings are produced by the architect and the C&S and M&E engineers. They set out the design intent: what is to be built, to what performance and where. With the specification they form the contract documents and the core construction documentation that the contractor prices and builds against, and the tender and construction drawings are developed from them. They do not normally tell a fabricator how to fabricate, weld, bend or fix each component.
The Wikipedia entry on shop drawings defines a shop drawing as a drawing or set of drawings produced by the contractor, supplier or manufacturer. On a construction project, shop drawings are typically created by the subcontractor or fabricator responsible for that component. Shop drawings are detailed drawings that translate design intent into fabrication and installation details: exact dimensions, materials, connection details, welding and fixings, tolerances and sequence.
Common types of shop drawings include:
Each is a submittal: it goes to the consultants for shop drawing review before the fabrication process starts. The consultant reviews and stamps each submission, and the review stamp shows whether work can proceed or the drawing must be revised and resubmitted.
Combined services drawings are an established Singapore term. The Singapore BIM Guide lists “Combined Services Drawings (CSD)” and “Single Services Drawings (SSD)” alongside shopdrawings and fabrication models. In the guide, these are documents that subcontractors and specialist subcontractors generate from the construction models. A CSD overlays the building services on the structure and architecture, so routes, levels and clearances can be agreed before installation. An SSD shows one service on its own. A Land Transport Authority paper on CSD/SEM coordination for Downtown Line 1 describes the same practice on rail work. Its authors note that planning plant rooms and ventilation shafts early was pivotal in minimising services congestion.
As-built drawings record the completed works, including every approved change, site instruction and field adjustment made during the construction process. The Singapore BIM Guide describes the as-built BIM element as “similar in level of detail to the Detailed Design stage, but updated with changes during the Construction stage”. A later Facility Management stage models elements as the actual constructed components. In other words, an as-built model is not a more detailed shop model. It is the design-level model corrected to match reality.
| Drawing type | Stage | Prepared by | Reviewed / accepted by | Purpose |
|---|---|---|---|---|
| Design drawings (incl. tender and construction drawings) | Design, tender, construction issue | Architect, C&S and M&E consultants | QPs for regulatory submissions; the employer under the contract | Define design intent and the scope to be priced and built |
| Shop drawings | Construction, before fabrication | Contractor, subcontractor, supplier or fabricator | Relevant consultants under the contract’s approval process | Set out the fabrication and installation of a component |
| Combined services drawings (CSD) | Construction, before services installation | Main contractor and M&E subcontractors, usually from a coordinated model | M&E and architectural consultants | Coordinate all services routes, levels and clearances on one set of drawings |
| Single services drawings (SSD) | Construction | Individual M&E subcontractor | M&E consultant | Install one service from coordinated information |
| As-built drawings / as-built model | Completion and handover | Contractor, updating throughout construction | Consultants, then QPs for TOP/CSC submissions | Record what was built for the owner, FM team and authorities |
The review column reflects common practice. The exact reviewer, review stamp wording and turnaround are set by each building contract and the project’s BIM Execution Plan.
The Wikipedia entry lists the information a shop drawing should carry. When consultants review shop drawings, they look for each item:
Reviewers also expect a proper title block, revision history, consistent symbols and abbreviations, references to contract drawing and specification clauses, and gridlines and levels that match the design model. Submissions are commonly returned when they are traced from superseded drawings, miss interfaces with other trades, or show ceiling-void services without coordinated levels.
The Singapore BIM Guide’s BIM Objective and Responsibility Matrix sets out the construction-stage sequence:
On public sector projects, BCA’s Public Sector Standard Conditions of Contract (PSSCOC) sets the contractual side. Under the PSSCOC for Construction Works 2020, contractor-designed works need the Superintending Officer’s written acceptance of the contractor’s drawings and specifications, with calculations, before execution (Clause 6.2). On substantial completion, the contractor submits O&M manuals and drawings of those works “as completed” (Clause 6.3). Private projects follow their own conditions of contract.
In a 2D computer-aided design (CAD) workflow, shop drawings are created trade by trade. Clashes surface when someone overlays the sheets, or on site. In a BIM workflow, the drawings come out of a model that has already been coordinated. A typical sequence:
Two cautions apply. First, a model only yields usable shop drawings if it is modelled to the right level of development and accuracy for fabrication; see our article on LOD 100 to 500. Second, fabricators of structural steel, precast and façade elements often bridge design and fabrication in their own specialist software. Their output still needs to come back into the federated model for checking.
The easiest as-built model to produce is one that was never allowed to fall behind. Every accepted revision, RFI, site instruction and variation that changes geometry or specification should go into the construction model while the people involved are still on site. The Singapore BIM Guide assumes this. The contractor continuously updates the model, supplies a record model for amendment submissions, and finally prepares the as-built model with the necessary third-party certifications.
Where the record has gaps, a laser survey and scan to BIM can be used to check or rebuild the affected areas. Typical gaps are concealed services that were never re-modelled, or existing parts of an addition and alteration project. For owners, the as-built model then becomes the starting point for asset information and COBie data; see our as-built, 6D BIM and COBie service.
Under CORENET X, building works pass through the Design Gateway, the Piling Gateway (where applicable) and the Construction Gateway before reaching the Completion Gateway, where TOP and CSC are obtained. Gateway Processes are mandatory for new projects of 5,000 sqm GFA and above from 1 October 2026; see our CORENET X Code of Practice guide. The CORENET X Code of Practice, 4th Edition (2026-09) states:
The Code’s summary of Completion Gateway requirements includes these as-built and record items:
| Agency | As-built / record items listed for TOP or CSC (summary) |
|---|---|
| BCA | Notice of Completion; completion of structural works; test records and site inspection where applicable; record plans; certificates of supervision (e.g. lightning protection, ACMV) |
| LTA | As-built topographic survey plans; for railway protection, endorsed as-built plans for foundation, structural and M&E where applicable; as-built M&E plans for handing over |
| PUB | As-built plans, survey plans or schematic sanitary drawing, with Form B1 clearance and relevant test reports |
| NParks | As-built plan and photo evidence of compliance with earlier approved submissions |
| URA | Declaration that works were built according to approved plans; as-built plan incorporating approved amendments and as-built works that QPs declared to have no material impact on planning controls |
| SCDF | Temporary Fire Permit and Fire Safety Certificate applications |
| NEA | Photo evidence of compliance and reports of completed works; site inspection for selected projects |
The Code adds that TOP/CSC checklists will guide project teams on as-built plan submissions, record plans, certificates of supervision and post-construction reports. Check the current Code and circulars for your project’s exact list. Shop drawings are not themselves a Completion Gateway submission; they are a contract matter. However, the as-built IFC models and plans the QPs submit must match what was actually installed from them.
No. Shop drawings are prepared before fabrication to show how work will be made and installed. As-built drawings are prepared at completion to record what was actually installed, including changes made after the shop drawings were accepted.
The contractor, subcontractor, supplier or fabricator responsible for that part of the works. BCA’s Singapore BIM Guide assigns shopdrawings, fabrication drawings, CSD and SSD to subcontractors and specialist subcontractors. The consultants then carry out the review of the shop drawings as part of the submittal process.
It depends on the contract. In the PSSCOC for Construction Works 2020, “Drawings” include drawings prepared by the contractor and accepted by the Superintending Officer under Clause 6.2. That acceptance does not relieve the contractor of its design responsibility. Check your own conditions of contract.
A combined services drawing shows all M&E services together with the structure, so routes, levels and clearances can be coordinated before installation. On BIM projects, CSDs are usually generated from a federated, clash-checked model.
For projects that submitted IFC models through CORENET X, the Code of Practice says as-built submissions consist of the latest updated IFC models with updated IFC+SG data. Agencies also list as-built plans and record plans for TOP/CSC. Projects below 5,000 sqm GFA that stay in CORENET 2.0 can use 2D or lightweight BIM.
Yes, if the same model is carried through construction. The coordinated model generates the CSD and shop drawings. Updating it with RFIs, variations and site changes turns it into the as-built model, from which as-built drawings and IFC exports are produced.