Shop Drawings vs As-Built Drawings: How BIM Produces Both

Shop Drawings vs As-Built Drawings: How BIM Produces Both

14 min read

Shop drawings show how a contractor or fabricator will make and install part of the works before it is built; as-built drawings (or an as-built model) record what was actually built once the work is complete. One looks forward and gets a design accepted for fabrication. The other looks back and becomes the record for the owner, the facility manager and, in Singapore, the agencies at the CORENET X Completion Gateway. On a BIM project, both can come from the same coordinated model, provided it is kept up to date.

On this page
  1. Types of drawings on a Singapore building project
  2. Comparison table: design, shop, CSD and as-built drawings
  3. Shop drawings vs construction drawings vs as-built drawings
  4. What a good shop drawing contains
  5. Who produces and approves each drawing on a Singapore project
  6. How BIM coordination produces shop drawings from a coordinated model
  7. From shop drawings to as-built records
  8. As-built records needed at the CORENET X Completion Gateway
  9. Common mistakes between shop drawing and as-built
  10. Frequently asked questions
  11. References

This guide compares design drawings, shop drawings, combined services drawings (CSD) and as-built drawings. It covers who prepares and reviews each on a Singapore project, what a good shop drawing contains, and how BIM coordination produces both sets of drawings.

Types of drawings on a Singapore building project

“Construction drawings” is often used for every sheet on site, but the drawings come from different parties, at different stages, for different reasons. BCA’s Singapore BIM Guide Version 2 lists shopdrawings, construction and fabrication models and the as-built model as separate BIM deliverables. It also treats design drawings, tender drawings, working drawings and as-built drawings as distinct sets.

Design drawings and construction drawings

During the design phase, design drawings are produced by the architect and the C&S and M&E engineers. They set out the design intent: what is to be built, to what performance and where. With the specification they form the contract documents and the core construction documentation that the contractor prices and builds against, and the tender and construction drawings are developed from them. They do not normally tell a fabricator how to fabricate, weld, bend or fix each component.

Shop drawings in construction

The Wikipedia entry on shop drawings defines a shop drawing as a drawing or set of drawings produced by the contractor, supplier or manufacturer. On a construction project, shop drawings are typically created by the subcontractor or fabricator responsible for that component. Shop drawings are detailed drawings that translate design intent into fabrication and installation details: exact dimensions, materials, connection details, welding and fixings, tolerances and sequence.

Common types of shop drawings include:

  • structural steel connection and erection drawings
  • rebar detailing
  • precast panel drawings
  • façade and curtain wall drawings
  • millwork, joinery and cabinetry drawings from a millwork shop
  • metalwork drawings for handrails, balustrades and staircases
  • MEP installation drawings for building systems such as ductwork, piping and cable trays

Each is a submittal: it goes to the consultants for shop drawing review before the fabrication process starts. The consultant reviews and stamps each submission, and the review stamp shows whether work can proceed or the drawing must be revised and resubmitted.

Combined services drawings (CSD) and single services drawings (SSD)

Combined services drawings are an established Singapore term. The Singapore BIM Guide lists “Combined Services Drawings (CSD)” and “Single Services Drawings (SSD)” alongside shopdrawings and fabrication models. In the guide, these are documents that subcontractors and specialist subcontractors generate from the construction models. A CSD overlays the building services on the structure and architecture, so routes, levels and clearances can be agreed before installation. An SSD shows one service on its own. A Land Transport Authority paper on CSD/SEM coordination for Downtown Line 1 describes the same practice on rail work. Its authors note that planning plant rooms and ventilation shafts early was pivotal in minimising services congestion.

As-built drawings and as-built models

As-built drawings record the completed works, including every approved change, site instruction and field adjustment made during the construction process. The Singapore BIM Guide describes the as-built BIM element as “similar in level of detail to the Detailed Design stage, but updated with changes during the Construction stage”. A later Facility Management stage models elements as the actual constructed components. In other words, an as-built model is not a more detailed shop model. It is the design-level model corrected to match reality.

Comparison table: design, shop, CSD and as-built drawings

Drawing typeStagePrepared byReviewed / accepted byPurpose
Design drawings (incl. tender and construction drawings)Design, tender, construction issueArchitect, C&S and M&E consultantsQPs for regulatory submissions; the employer under the contractDefine design intent and the scope to be priced and built
Shop drawingsConstruction, before fabricationContractor, subcontractor, supplier or fabricatorRelevant consultants under the contract’s approval processSet out the fabrication and installation of a component
Combined services drawings (CSD)Construction, before services installationMain contractor and M&E subcontractors, usually from a coordinated modelM&E and architectural consultantsCoordinate all services routes, levels and clearances on one set of drawings
Single services drawings (SSD)ConstructionIndividual M&E subcontractorM&E consultantInstall one service from coordinated information
As-built drawings / as-built modelCompletion and handoverContractor, updating throughout constructionConsultants, then QPs for TOP/CSC submissionsRecord what was built for the owner, FM team and authorities

The review column reflects common practice. The exact reviewer, review stamp wording and turnaround are set by each building contract and the project’s BIM Execution Plan.

Shop drawings vs construction drawings vs as-built drawings

  • Timing. Construction drawings say what should be built. Shop drawings say how it will be built. As-built drawings say what was built.
  • Author. Construction drawings come from architects and engineers. Shop drawings come from the fabricator or installer. As-built records are usually compiled by the contractor and checked by the consultants.
  • Detail. Shop drawings carry the most detail (bolt sizes, bar marks, hanger spacing, panel joints). The Singapore BIM Guide notes that construction-stage details such as rebar can be shown in 3D or in 2D shopdrawings. As-built drawings return to design-level detail, updated for changes.
  • Contract status. Shop drawings are produced to satisfy the contract documents, not to replace them. Whether an accepted shop drawing becomes part of the contract drawings depends on the contract (see the FAQ).

What a good shop drawing contains

The Wikipedia entry lists the information a shop drawing should carry. When consultants review shop drawings, they look for each item:

  • Comparison information so the architect and engineers can check the item against the specification and design drawings, such as product data from the supplier, material grades and finishes.
  • Changes: any deviation from the construction documents clearly identified.
  • Fabrication details: dimensions, conventions and special fabrication instructions complete enough for the fabricator to work from the shop drawing alone.
  • Field verification: dimensions that must be checked on site before anyone starts to fabricate, such as slab levels, openings and existing services.
  • Installation: placement, fixing and sequence, with plans, sections and elevations as needed.
  • Samples, where colour or texture must be approved physically.

Reviewers also expect a proper title block, revision history, consistent symbols and abbreviations, references to contract drawing and specification clauses, and gridlines and levels that match the design model. Submissions are commonly returned when they are traced from superseded drawings, miss interfaces with other trades, or show ceiling-void services without coordinated levels.

Who produces and approves each drawing on a Singapore project

The Singapore BIM Guide’s BIM Objective and Responsibility Matrix sets out the construction-stage sequence:

  1. The contractor starts and continuously updates the Detailed Design BIM model towards an As-Built BIM model. The employer specifies the as-built modelling requirements.
  2. Construction models are produced, in stages, from the architectural, structural and MEP models, with key services coordinated.
  3. Subcontractors and specialist subcontractors generate shopdrawings, fabrication models and drawings, CSD and SSD from the construction models.
  4. Where an amendment submission is needed, the contractor gives the consultants the latest record model and model-generated drawings.
  5. The contractor prepares the final As-Built BIM model, reflecting amendments and the verified completed construction. The consultants confirm it corresponds to the final approved amendment plans submitted to the authorities.

On public sector projects, BCA’s Public Sector Standard Conditions of Contract (PSSCOC) sets the contractual side. Under the PSSCOC for Construction Works 2020, contractor-designed works need the Superintending Officer’s written acceptance of the contractor’s drawings and specifications, with calculations, before execution (Clause 6.2). On substantial completion, the contractor submits O&M manuals and drawings of those works “as completed” (Clause 6.3). Private projects follow their own conditions of contract.

How BIM coordination produces shop drawings from a coordinated model

In a 2D computer-aided design (CAD) workflow, shop drawings are created trade by trade. Clashes surface when someone overlays the sheets, or on site. In a BIM workflow, the drawings come out of a model that has already been coordinated. A typical sequence:

  1. Develop discipline models. Architectural, structural and MEP models are developed to construction-level detail, typically in Autodesk Revit (see our Revit BIM modelling service). The Singapore BIM Guide recommends checking each model as “fit for coordination” before sharing.
  2. Federate and run clash detection. The models are combined in a tool such as Navisworks, where the coordinator can add and run clash tests and track their status. Our guide to clash detection in BIM projects covers test set-up.
  3. Resolve and freeze. The Singapore BIM Guide says discrepancies should be recorded and sent to model owners in coordination reports. It recommends freezing and signing off the revised model once the issues are resolved. This is the core of BIM coordination.
  4. Create shop drawings from the model. Orthographic views (plans, sections and elevations) and details for the CSD, SSD and trade shop drawings are cut from the frozen model, then dimensioned and annotated. The guide recommends generating 2D drawings directly from the BIM model and clearly labelling any 2D detail not produced from it.
  5. Review, revise, reissue. When a consultant comments or the design changes, the model is updated and the sheets regenerated. Autodesk’s Revit documentation says all views are live: a change in one view is instantly propagated to the other views of the model.

Two cautions apply. First, a model only yields usable shop drawings if it is modelled to the right level of development and accuracy for fabrication; see our article on LOD 100 to 500. Second, fabricators of structural steel, precast and façade elements often bridge design and fabrication in their own specialist software. Their output still needs to come back into the federated model for checking.

From shop drawings to as-built records

The easiest as-built model to produce is one that was never allowed to fall behind. Every accepted revision, RFI, site instruction and variation that changes geometry or specification should go into the construction model while the people involved are still on site. The Singapore BIM Guide assumes this. The contractor continuously updates the model, supplies a record model for amendment submissions, and finally prepares the as-built model with the necessary third-party certifications.

Where the record has gaps, a laser survey and scan to BIM can be used to check or rebuild the affected areas. Typical gaps are concealed services that were never re-modelled, or existing parts of an addition and alteration project. For owners, the as-built model then becomes the starting point for asset information and COBie data; see our as-built, 6D BIM and COBie service.

As-built records needed at the CORENET X Completion Gateway

Under CORENET X, building works pass through the Design Gateway, the Piling Gateway (where applicable) and the Construction Gateway before reaching the Completion Gateway, where TOP and CSC are obtained. Gateway Processes are mandatory for new projects of 5,000 sqm GFA and above from 1 October 2026; see our CORENET X Code of Practice guide. The CORENET X Code of Practice, 4th Edition (2026-09) states:

  • The Completion Gateway is a one-stop dashboard of TOP/CSC status across agencies. TOP submissions are made to each agency independently, whenever ready.
  • If IFC models were submitted earlier in CORENET X, as-built submissions consist of the latest updated IFC models, with IFC+SG data updated from the earlier approved models.
  • Teams should verify the 2D and 3D documentation required, especially documentation created by parties onboarded later in the project.
  • The overall TOP/CSC is released only when all agencies’ clearances are obtained.

The Code’s summary of Completion Gateway requirements includes these as-built and record items:

AgencyAs-built / record items listed for TOP or CSC (summary)
BCANotice of Completion; completion of structural works; test records and site inspection where applicable; record plans; certificates of supervision (e.g. lightning protection, ACMV)
LTAAs-built topographic survey plans; for railway protection, endorsed as-built plans for foundation, structural and M&E where applicable; as-built M&E plans for handing over
PUBAs-built plans, survey plans or schematic sanitary drawing, with Form B1 clearance and relevant test reports
NParksAs-built plan and photo evidence of compliance with earlier approved submissions
URADeclaration that works were built according to approved plans; as-built plan incorporating approved amendments and as-built works that QPs declared to have no material impact on planning controls
SCDFTemporary Fire Permit and Fire Safety Certificate applications
NEAPhoto evidence of compliance and reports of completed works; site inspection for selected projects

The Code adds that TOP/CSC checklists will guide project teams on as-built plan submissions, record plans, certificates of supervision and post-construction reports. Check the current Code and circulars for your project’s exact list. Shop drawings are not themselves a Completion Gateway submission; they are a contract matter. However, the as-built IFC models and plans the QPs submit must match what was actually installed from them.

Common mistakes between shop drawing and as-built

  • Shop drawings drafted outside the model. When trades draft in CAD from PDFs, the model and the installed works drift apart, and as-built work becomes a survey exercise.
  • No named owner for model updates. The BIM Execution Plan should say who updates the model for each RFI, variation and accepted shop drawing, and when. Otherwise as-built work is left to the end and relies on marked-up prints.
  • Late-appointed parties. Specialists brought in late may not follow the project’s IFC+SG conventions, which is why the Code flags their documentation.

Frequently asked questions

Are shop drawings the same as as-built drawings?

No. Shop drawings are prepared before fabrication to show how work will be made and installed. As-built drawings are prepared at completion to record what was actually installed, including changes made after the shop drawings were accepted.

Who prepares shop drawings in Singapore?

The contractor, subcontractor, supplier or fabricator responsible for that part of the works. BCA’s Singapore BIM Guide assigns shopdrawings, fabrication drawings, CSD and SSD to subcontractors and specialist subcontractors. The consultants then carry out the review of the shop drawings as part of the submittal process.

Do approved shop drawings override the contract drawings?

It depends on the contract. In the PSSCOC for Construction Works 2020, “Drawings” include drawings prepared by the contractor and accepted by the Superintending Officer under Clause 6.2. That acceptance does not relieve the contractor of its design responsibility. Check your own conditions of contract.

What is a CSD in construction?

A combined services drawing shows all M&E services together with the structure, so routes, levels and clearances can be coordinated before installation. On BIM projects, CSDs are usually generated from a federated, clash-checked model.

Is an as-built BIM model required under CORENET X?

For projects that submitted IFC models through CORENET X, the Code of Practice says as-built submissions consist of the latest updated IFC models with updated IFC+SG data. Agencies also list as-built plans and record plans for TOP/CSC. Projects below 5,000 sqm GFA that stay in CORENET 2.0 can use 2D or lightweight BIM.

Can BIM produce both shop drawings and as-built drawings?

Yes, if the same model is carried through construction. The coordinated model generates the CSD and shop drawings. Updating it with RFIs, variations and site changes turns it into the as-built model, from which as-built drawings and IFC exports are produced.

References

  1. CORENET X Code of Practice, Fourth Edition (CORENET X COP 4 Edition 2026-09). CORENET X / Building and Construction Authority, September 2026. https://info.corenet.gov.sg/docs/default-source/default-document-library/corenet-x-cop—4-edition-2026.pdf
  2. Singapore BIM Guide Version 2. Building and Construction Authority, 2013. https://info.corenet.gov.sg/docs/default-source/bim-guides/singapore/singapore-bim-guide_v2.pdf
  3. Public Sector Standard Conditions of Contract (PSSCOC). Building and Construction Authority. https://www1.bca.gov.sg/growth-and-transformation/procurement/standard-contract-forms/public-sector-standard-conditions-of-contract-psscoc/
  4. PSSCOC for Construction Works 2020 (8th edition, July 2020). Building and Construction Authority. https://isomer-user-content.by.gov.sg/338/5349d125-0337-4dc3-a36d-623e599f2865/1-psscoc-for-construction-works-2020.pdf
  5. Liw, R. C. W., Chua, E. and Chou, M. “In-house Combined Services Drawing / Structural, Electrical & Mechanical (CSD/SEM) Coordination and Drawing Production for Downtown Line 1 (DTL1) Promenade Station and Tunnels”. Land Transport Authority; WUTC 2010. https://rpsonline.com.sg/proceedings/9789810863968/html/978-981-08-6396-8_T2-02.php
  6. Shop drawing. Wikipedia. https://en.wikipedia.org/wiki/Shop_drawing
  7. Modeling – Essential Skill (Revit 2023 Help). Autodesk. https://help.autodesk.com/cloudhelp/2023/ENU/Revit-GetStarted/files/GUID-E66946AE-64B0-448D-8357-65F30F643F39.htm
  8. To Manage Clash Tests (Navisworks 2020 Help). Autodesk. https://help.autodesk.com/cloudhelp/2020/ENU/Navisworks/files/GUID-3EDAA609-92D2-4C76-A319-6B7C06D93AEB.htm