4D BIM Construction Sequencing Model
Time-linked 3D BIM model for MRT tunnel construction — animating the full construction sequence from TBM launch shaft excavation through tunnel boring drive operations, enabling programme visualisation, schedule risk identification, and stakeholder communication.
Beyond+
What is 4D BIM ?
3D
Geometry Model
Programmed Schedule
4D
Time-linked simulation of construction activities — every model element linked to a programme task, enabling visual playback of the build sequence.
Project Details
Project Reference
MRT Tunnel — 4D BIM Construction Sequencing Model
Client / Owner
Land Transport Authority (LTA), Singapore
Project Type
MRT Tunnel Construction — TBM Launch Shaft & Drive
Main Contractor
Confidential
BIM Dimension
4D — Time-linked Construction Sequencing
Key Activities
Launch Shaft RC Works · TSA Shaft Wall · TBM 2nd Drive
4D Software
Autodesk Navisworks Manage — TimeLiner Module
Programme Link
Gantt Programme (P6 / MS Project) linked to BIM model
Project Status
Completed — FM Model Handed Over

Fig. 1
4D Construction Sequence — Key Phases
Phase 1
Launch Shaft Preparation
Launch Shaft Preparation
Excavation, sheet piling, and temporary strutting arrangement (TSA) installation
Phase 2
Launch Shaft RC Works
Launch Shaft RC Works
Reinforced concrete shaft base, walls, and structural lining construction
Phase 3
TSA Shaft Wall Construction
TSA Shaft Wall Construction
Middle waler installation and east shaft wall construction to TSA specification
Phase 4
TBM Assembly & Launch
TBM Assembly & Launch
TBM component lowering, assembly in launch shaft, and ground-breaking launch
Phase 5
TBM 2nd Drive
TBM 2nd Drive
TBM boring from FB Shaft to CR117 — 1,438 m continuous drive with segment ring erection
Phase 6
Tail Grouting & Handover
Tail Grouting & Handover
Annular grouting, convergence monitoring, and tunnel as-built verification
Scope Of Work


Key Deliverables
4D BIM model (Navisworks NWD) — 3D model fully linked to construction programme with TimeLiner tasks
4D animation video — construction sequence rendered as MP4 for stakeholder review and public communication
Programme task mapping schedule — listing all BIM objects linked to programme activities
Construction sequence report — written narrative of phased construction activities with 4D screenshots
Programme risk register — schedule conflicts and sequence clashes identified through 4D review
As-built 4D model update — model updated to reflect actual construction progress vs. planned sequence
Why This Matters
Visual Programme
Anyone can understand the construction sequence — not just engineers. 4D animation communicates the plan to clients, regulators, and the public without reading a Gantt chart.
Sequence Conflict Detection
Spatial clashes between concurrent construction activities found in the model — before they cause delays on site.


TBM Drive Simulation
Full 1,438 m TBM drive animated ring by ring — allowing the team to review and optimise the tunnelling sequence before boring begins.
LTA BIM Compliant
4D BIM delivered to LTA BIM standards — ready for Design Review, construction methodology approval, and regulatory submissions.
Tools & Standards
4D Software
Autodesk Navisworks Manage — TimeLiner Module
BIM Authoring
Autodesk Revit (Civil + Structural Worksets)
Programme Import
Primavera P6 / Microsoft Project (MPP) Gantt integration
Animation Export
AVI / MP4 video export from Navisworks Animator
Standards
LTA BIM Standards, LTA TBM Tunnelling Specification, ISO 19650
Documentation
4D screenshots, sequence reports, programme mapping schedule
Legal Notice & Confidendiality Statement
This portfolio page is published for marketing and capability demonstration purposes only. All images, model views, programme data, and technical descriptions are used with the knowledge of the project owner and do not disclose any proprietary, confidential, or For-Construction (IFC) design or programme information. Construction chainage references and task names shown are representative of scope — no exact alignment coordinates, tender programme data, or commercially sensitive scheduling information are disclosed. The identity of the Main Contractor has been withheld in
accordance with contractual confidentiality obligations. Published content complies with Singapore’s Copyright Act 2021, the Personal Data Protection Act (PDPA), and applicable non-disclosure provisions. Beyond+ Pte Ltd retains all intellectual property rights over BIM deliverables produced under this engagement.
accordance with contractual confidentiality obligations. Published content complies with Singapore’s Copyright Act 2021, the Personal Data Protection Act (PDPA), and applicable non-disclosure provisions. Beyond+ Pte Ltd retains all intellectual property rights over BIM deliverables produced under this engagement.